FOR IMMEDIATE RELEASE06-14
March
14, 2006
Contact:
Ian Michaels
(718) 595-6600
Ashokan
Release Channel to Open This Week
Testing
to begin Wednesday with full operation possible by end of week
|
DEP
engineer Sean McAndrew (right, pointing) shows Commissioner
Emily Lloyd (center) some of the work that was done to wake
the Ashokan Release Channel ready for use. In this area barricades
were erected to direct the flow of water away from buildings
that are part of the Ashokan Field Campus. Up to 600 million
gallons of water per day will flow through the channel from
the Ashokan Reservoir in order to decrease the chance of
flooding in downstream communities along the lower Esopus
Creek. |
Commissioner Emily Lloyd of the New York City Department of Environmental
Protection (DEP) today announced that the Ashokan Release Channel will
be opened this week. With weather conditions permitting, the
channel will be tested on Wednesday, March 15 and could be fully
operational by the end of the week.
“The DEP has gone through great effort to re-open the release channel
in order to provide some relief to people living downstream,” said
Commissioner Lloyd. “Water levels in the Ashokan Reservoir
have been above normal since the record rainfall we received in October,
and they’ll likely remain high throughout the spring. But
with this step we will be able to make controlled releases from the reservoir
to help protect property along the lower Esopus.”
Water from the release channel flows through the Beaver Kill into the Old
Esopus Creek, which flows through the SUNY New Paltz Ashokan Field Campus
on its way to the lower Esopus Creek. The last time the channel was operated
was in 1992. Once testing is complete and full flow is restored,
up to 600 million gallons per day (MGD) of water will be able to flow
through.
The DEP has leased the entire Ashokan Field Campus through mid-June in
order to re-open the channel. Significant improvement work, including
the construction of berms and barriers, had to be performed in order to
protect campus buildings from possible flooding and to accommodate the
anticipated flows in the Old Esopus Creek. Even with those improvements,
it is expected that part of the campus may be flooded.
The only other controlled method for water to exit the Ashokan Reservoir
is through the Catskill Aqueduct, which conveys drinking water to users
south of Ulster County. The DEP has increased its intake through
the aqueduct from a normal flow of 300 - 350 million gallons per day (MGD)
to the aqueduct’s maximum capacity of 580 MGD. However, flow
into the reservoir has often exceeded that amount and the reservoir has
largely been above capacity and spilling into the lower Esopus since October,
when the region received over 12 inches of rain.
The high water conditions at Ashokan have been affected by the need to
remove water from the Schoharie Reservoir in order to accomplish the ongoing
stabilization project at the Gilboa Dam. Water from Schoharie is
diverted through the Shandaken Tunnel, which outlets into the upper Esopus
Creek.
The release channel would be operated when water levels in the lower Esopus
were below flood stage, with the intent of creating a void in the reservoir
to capture flow from the Shandaken Tunnel as well as the anticipated annual
runoff from the coming spring thaw. The DEP has created detailed
parameters for channel operations based on variables such as weather and
water elevations within the lower Esopus.
Testing of the channel will include monitoring the effect of water flow
at numerous locations along the path of the water. A small flow
of approximately 100 MGD will be used Wednesday to test the integrity
of the channel. A flow of up to 400 MGD is expected by Thursday,
with higher flows being gradually implemented through the end of the week.