CB10 Street Activity/Block Party Permit GuidelinesNational Grid Scheduled Work Notification
Major Street Events within Community Board 10 – Summary
DSNY Reminder about placing garbage for pickup
Important News from the MTA - NYC Transit - N Line Construction
2017 Alternate Side Parking Rules Suspension Calendar
Construction Notification
DOT Bicycle Network within Community Board 10
Animal Care Centers of NYC
Immigration Advocacy Services
N Train Station Rehab Presentation

 

Fireworks Display near Fort Hamilton

 

On Saturday, July 1 at 9:45 pm there will be a fireworks display on barges near Fort Hamilton in Brooklyn.

 

FLASH

City Council District 43,

 


On Thursday June 29 2017 a Commercial for "Trop 50 TVC" is scheduled to film scenes at the following locations:

 

 
Int Spin Class
238 BAY RIDGE AVE, Brooklyn (Interior)
Description: Woman Takes Spin Class
VTU Request: Yes
Trucks: 1
Meeting Place: Wed 6-28, 10p, SW Corner of Bay Ridge Ave and 3rd Ave, Brooklyn. Signs Posted Monday, 6-26.
Request: 40ft Scissor lift in Curb Lane IFO location for lighting Platform
06/29/2017 06:00 AM
06/29/2017 10:00 PM
PARKING REQUESTS
PARKING REQUEST
  • BAY RIDGE AVENUE between RIDGE BOULEVARD and 3 AVENUE
    • Street Side: South
    • Street Control: Full Block
  • BAY RIDGE AVENUE between RIDGE BOULEVARD and 3 AVENUE
    • Street Side: North
    • Street Control: 2 Truck Lengths
  • 3 AVENUE between OVINGTON AVENUE and 68 STREET
    • Street Side: West
    • Street Control: Full Block
  •  



    Permit# 360555

    If you have further questions you can contact their Locations Department at (310) 315-8700





     

    Notice of Street Closure due to Crane Operation - Ovington Avenue between 3rd and 4th Avenue

    CS Scott will conduct crane operations at 364 Ovington Avenue on Saturdays between 8 am and 4 pm from June 30th through July 30th and Ovington Avenue from 3rd to 4th Avenue will be closed to vehicular traffic.  Signs will be posted in advance of each street closure.  For any questions, please contact CS Scott at 718-797-9555.

     

    NYC Ferry

    Please see the attached flyer regarding the NYC Ferry which launched in Bay Ridge on Thursday, June 1st.
    NYC Ferry

    ADVENTURES NYC

    Please see the flyer below for information on Adventures NYC.
    Adventures NYC

    NATIONAL GRID PLANNED CONSTRUCTION WORK

    In the coming weeks National Grid has planned construction to improve the reliability of its gas system.  Work is scheduled to take place at the following locations:

    On Bay Ridge Parkway between 4th and 5th Avenue

    On 5th Avenue between Bay Ridge Parkway and 76th Street

    On 5th Avenue between Bay Ridge Parkway and 74th Street

    Typically, work performed by National Grid will begin with the installation of new gas pipe either in the street or sidewalk.  The excavation required will be backfilled at the end of each day.  Steel plates will be used to cover any excavations left open
       
        allow vehicular traffic, and provide access to driveways, steps, and walkways.
                         
        The entire work area will be kept clean and orderly, and attempts will be made to keep noise, dust, and debris to a minimum.  All material required on site will be stored neatly in designated areas.
       
       
                         
        All or part of your gas service may have to be replaced.  In order to complete this work, we must gain access to your home at the point where the service enters the building (basement, crawlspace, etc.).  If this is the case, you will be contacted by a
       
        National Grid representative to make an appointment.
                         
                         
                         
        Some excavations may need to remain open until all gas services have been transferred, at which point the old main will be retired and the openings backfilled.
       
       
        All street & sidewalk surfaces affected by the construction will be repaved to ensure a smooth surface.  Temporary asphalt pavement will be used until all National Grid work is complete and permanent restoration can be performed.
     
       
        Concrete openings should be restored within 21 days, with the exception of work done in mid-winter.  Some delays may occur due to inclement weather or when the temperature is too cold to pour concrete.

     

    April 05, 2017

    Traffic Pattern Shift at Verrazano-Narrows Bridge Staten Island-bound Toll Plaza

    Starting this weekend, a change in traffic pattern will be in place on the westbound (to Staten Island) toll plaza coming off the Upper and Lower Levels of the Verrazano-Narrows Bridge. The change is necessary to accommodate the next stage of work for installation of the Cashless Tolling structures and associated systems. 

    As with the previous stage, several toll lanes will be closed at a time to accommodate the work zone activity. All lanes on the upper and lower levels of the bridge itself will be maintained during peak hours.

    Work includes roadway replacement, demolition, excavation and concrete placement, as well as electrical and drainage systems and new signage. Cashless Toll collection is set to start in the summer of 2017 at the Verrazano-Narrows Bridge.

    Motorists are advised to allow additional travel time. 

    Motorists can sign up for MTA e-mail or text alerts at www.mta.info and check the Bridges and Tunnels homepage or Facebook page for the latest information on this planned work.

    NATIONAL GRID PLANNED CONSTRUCTION WORK IN CB 10

                  March 23, 2017
                         
    In the coming weeks, National Grid has planned construction in your district and this notification will provide information on
    the project.  This work is required due to the pending replacement of existing municipal facilities (i.e., water, sewer, catch
    basins, sidewalks, etc.).  If you seek additional information, please reference the following:
                         
    Construction due to: CAPITAL CONSTRUCTION   Billing Unit: 201
    Reference Number: Encroachment   Community Board: 10
                         
                         
                         
        Scope: 55 ft Typical Trench Width: 2 ft Approx. Duration [days]: 30  
                         
        Locations                
        On Street: Cross Street 1: Cross Street 2 (if applicable):
                         
        73rd St 3rd Ave 4th Ave
        73rd St 3rd Ave Ridge Blvd
        73rd St 3rd Ave Intersection
        3rd Ave 73rd St 72nd St
        3rd Ave 73rd St 74th St
             

     

     

    National Grid Notice of Upcoming Work

    National Grid Capital Construction work is scheduled to take place beginning in the upcoming weeks at the following locations:

    Scope: 150 ft Typical Trench Width: 2 ft Approx. Duration [days]: 30  
                     
    Locations                
    On Street: Cross Street 1: Cross Street 2 (if applicable):
                     
    Senator St Ridge Blvd 3rd Ave
         
                         
                         
        Scope: 1500' Typical Trench Width: 2 ft Approx. Duration [days]: 90  
                         
        Locations                
        On Street: Cross Street 1: Cross Street 2 (if applicable):
                         
        86 St 12 Ave  13 Ave
        86 St 13 Ave INT
        13 Ave 86 St 85 St
        86 St 13 Ave 14 Ave
        86 St 14 Ave INT
        14 Ave 85 St 86 St
        14 Ave 86 St Benson Ave
        86 St 14 Ave 15 Ave
        86 St 15 Ave INT
        15 Ave 85 St 86 St
        15 Ave 86 St Benson Ave
        86 St 15 Ave 16 Ave

     

           
                       
                         
        Typically, work performed by National Grid will begin with the installation of new gas pipe either in the street or sidewalk.  The excavation required will be backfilled at the end of each day.  Steel plates will be used to cover any excavations left open
       
        allow vehicular traffic, and provide access to driveways, steps, and walkways.
                         
        The entire work area will be kept clean and orderly, and attempts will be made to keep noise, dust, and debris to a minimum.  All material required on site will be stored neatly in designated areas.
       
       
                         
        All or part of your gas service may have to be replaced.  In order to complete this work, we must gain access to your home at the point where the service enters the building (basement, crawlspace, etc.).  If this is the case, you will be contacted by a
       
        National Grid representative to make an appointment.
                         
                         
                         
        Some excavations may need to remain open until all gas services have been transferred, at which point the old main will be retired and the openings backfilled.
       
       
        All street & sidewalk surfaces affected by the construction will be repaved to ensure a smooth surface.  Temporary asphalt pavement will be used until all National Grid work is complete and permanent restoration can be performed.
       
       
        Concrete openings should be restored within 21 days, with the exception of work done in mid-winter.  Some delays may occur due to inclement weather or when the temperature is too cold to pour concrete.
       
       

     

    CB10 Street Activity/Block Party Permit Guidelines

    Block Party Guidelines

    Block Party Guidelines

     

    MTA Bridges & Tunnel Notification of work on the Verrazano-Narrows Bridge

    The start of toll plaza construction activities in the Upper Level westbound toll plaza will begin on Tuesday, January 10th.  This work requires a barricaded work zone to set up the systems and ganrty structures necessary for future Cashless Tolling conversion at the Verrazano-Narrows Bridge, set for summer 2017.  The prep work is scheduled to start Tuesday, January 10th and will continue through June, in advance of the switch to Cashless. The MTA Bridge team will be monitoring traffic and safety, and doing everything possible to mitigate any traffic issues.  Work will also include replacement of concrete pavement, new drainage, etc.

    The work area will initially be located in the westbound plaza far left toll lanes (two-to-three toll lanes in the first stage).  The area will be reconstructed in stages to maintain optimal traffic flow.  After a standard period of motorist adjustment to the new traffic pattern shift we can expect moderate impact; that said, note that there will be no construction on the eastbound (to Bklyn) side to impact the morning rush; work is westbound only.  Also, there is no loss in traffic lanes on the bridge span itself for peak periods -just the toll plaza area where the gantry structure will eventually go.  The exception, of course, is the ongoing Upper Level deck reconstruction that requires a permanent lane closure in the off-peak direction (project progressing well and on schedule).

    The MTA will continue to provide updates in the coming weeks and months about Cashless Tolling, which allows more efficient and safe traffic flow (no more merging or crossing over to choose a toll payment lane) and is better for the environment, as drivers no longer wait to pay cash or get stuck behind vehicles with E-ZPass issues.

    Cable Excavation Work in Community Board Ten

    JEK Communications, Inc. has been retained by"Cablevision of New York" to perform excavation of the existing cable television system on 64th Street between 7th Avenue and 8th Avenue.  The work will begin no more than 3 days from this notification.  Work will be performed 1-7 days and all work completed will be restored to its original state prior to work start.

    Department of Sanitation Snow Removal Information

    Please see the link below for information from the Department of Sanitation regarding snow removal FAQ
    Snow Removal Info

    Water Main Replacement Work Coming to Dyker Heights

    Community Board Ten has been notified by the NYC Department of Design and Construction (DDC) that the existing water mains at the below locations need to be replaced in order to improve water distribution.

    The water main replacement project commenced along 14th Avenue at 76th Street and will continue at the locations listed below over the next few weeks - weather permitting. 

    - 14th Avenue and 76th Street
    - 12th Avenue - Bay Ridge Parkway to 81st Street
    - 13th Avenue - Bay Ridge Parkway to 81st Street
    - 76th Street to 81st Street - 12th to 14th Avenues

    The New York City Department of Design and Construction community liaison will be distributing leaflets to affected blocks before work begins.

    2017 Alternate Side Parking Rules Suspension Calendar

    The schedule for Alternate side Parking suspension dates for 2017 is now available at the Community Board 10 District Office, 8119 5th Avenue.
    You can view the schedule below, or stop by the office to pick one up.
    2017 ASP Parking Rules Suspension Calendar

    Free Monthly Land Use Clinics

    Please see the flyer below for details on free monthly land use clinics sponsored and hosted by Council Member Vincent Gentile.
    Free Monthly Land Use Clinics

    Notice of Upcoming Work - Street Restoration

    Please see the flyer below for information on ongoing work on the Siphon Project on Shore Road and 79th Street which began on October 10, 2016 and will contiue for approximately 8 weeks (weather permitting).
    Siphon Project Update

    Notification from DSNY - BULK PICK UP CHANGES IN COMMUNITY BOARD 10

    If you live in Bay Ridge, Dyker Heights or Fort Hamilton there are changes in Bulk Pick Up.  The Department of Sanitation uses a dual-bin truck for trash and organics collection.  Due to size limitations, bulk items larger than 4 feet by 3 feet cannot be collected using dual-bin trucks.  If you are throwing out bulk items larger than 4 feet by 3 feet, such as mattresses, couches, or large pieces of furniture, etc., place them out after 4PM the evening before your last scheduled collection day of each week.  These items will be collected by the end of day on Saturday. 

    Brooklyn Public Library Volunteer Opportunities

    Please see the flyers below for Volunteer opportunities available at the Brooklyn Public Libraries.
    Bklyn Public Library

    Include NYC Flyer

    DSNY Reminder about placing garbage for pickup

    Reminder - all garbage and recycling must be placed curbside after 5:00 pm on the night before your scheduled pickup day. There are times when the Sanitation Department must alter their schedule and will possibly pick up on the overnight shift or in the very early hours of your scheduled pick up day. (Posted: January 22, 2016)

    Important News from the MTA - NYC Transit - N Line Construction

    As you know, in January of this year NYCTransit started a 48 month construction project to renew nine stations along the Sea Beach N Line in Brooklyn from 8th Avenue to 86th Street. Over the past year we have been in the preliminary construction phase prepping for the major work that will start next month, January 2016.

    Phase I of the project will see major construction work on the Manhattan-bound station platforms, platform walls, stairs, etc. In order to safely and efficiently perform this work track access is necessary. Starting Monday, January 18, 2016, Manhattan-bound platforms at all nine (9) stations will be out of service for 14 months. There will be temporary platforms at the 8th Avenue and Bay Parkway stations. To access the Fort Hamilton Parkway, New Utrecht Ave, 18th Ave, 2nd Ave, Kings Highway, Avenue U and 86th Street stations while platforms are under constructions, customers will need to back-ride using the temporary platforms at 8th Avenue and Bay Parkway or travel to Stillwell Terminal.

    Customer Service Notices and take-ones will be going out into stations and trains, announcements on trains and in Stations, as well as social media outlets in the weeks before the January 18 start date. (Posted: January 07, 2016)

    DOT Bicycle Network within Community Board 10

    Click on the link below to view the updated DOT Bicycle Network within Community Board 10. (Posted: October 13, 2015)

    Animal Care Centers of NYC

    Please see the information below regarding Animal Care Centers of NYC (formerly Animal Care & Control of NYC). (Posted: September 21, 2015)

    Immigration Advocacy Services

    Please see the flyer below for information on Immigration Advocacy Services that are available. (Posted: September 17, 2015)

    N Train Station Rehab Presentation

    Please see attached MTA presentation for rehabilitation plan for stations along the N line beginning January 2016. This project is expected to last for 48 months.

    Click the link for the full presentation. (Posted: September 15, 2015)


    Announcements