NYC DOT and NYC DDC Announce Milling and Paving of Canal Street to Begin Next Week

Contracted milling and paving managed by the NYC Department of Design and Construction begins Monday night, May 2nd and is expected to last 3 weeks

The New York City Department of Transportation and the New York City Department of Design and Construction today announced that the milling and paving process along Canal Street, spanning from Varick Street to Allen Street, will begin Monday night, May 2nd at 8 P.M.

Work, which includes incidental pedestrian ramp and curb repairs, is expected to continue each weeknight for approximately 3 weeks between the hours of 8 PM and 5 AM. The work will begin at Varick Street and proceed east curb to curb to Allen Street. There will be intermittent lane closures throughout the duration of the process.  