PHASE l. BEGINNING THE LEGALIZATION PROCESS

1. Owner begins complying with the legalization process required in Article 7-C of the Multiple Dwelling Law (Loft Law) by filing an alteration application and plans with Department of Buildings (DOB).

2. DOB reviews plans and issues Objection Sheet and list of requirements, which includes obtaining Loft Board Certification.

3. Owner files plans with Loft Board as part of Narrative Statement. Loft Board holds Narrative Statement conference with Owner and Tenants to resolve issues relating to proposed legalization work.

4. DOB approves Owner's plans when all issues are cleared, including Loft Board Certification.


PHASE II. OBTAINING WORK PERMIT, BEGINNING CONSTRUCTION, DOCUMENTING ARTICLE 7-B COMPLIANCE (FIRE SAFETY)

5. Owner obtains work permit and files it with the Loft Board.

6. Owner begins legalization work. Loft Board meets with owner to monitor progress and provide assistance. Owner submits monthly status reports to the Loft Board

7. Owner complies with Article 7-B by completing required work items and DOB filings; Owner then documents compliance by filing Article 7-B Compliance Form or Temporary Certificate of Occupancy (TCO) with the Loft Board.


PHASE III. COMPLETING THE WORK AND OBTAINING A CERTIFICATE OF OCCUPANCY

8. Owner completes all work to obtain a final Certificate of Occupancy (C of O), resolves any open DOB applications, and removes any DOB and Environmental Control Board (ECB) violations.

9. Owner requests C of O inspection from DOB. After issuance of all DOB sign-offs, DOB requests Loft Board review as to whether it should issue the C of O.

10. If owner is in compliance with Loft Board requirements, Loft Board notifies owner and DOB that it does not object to issuance of the C of O.

11. DOB issues the final C of O.


PHASE IV. SETTING LEGAL RENTS AND REMOVING BUILDING FROM LOFT BOARD JURISDICTION

12. Within 9 months of issuance of the final C of O, the owner may apply for rent increase based upon code compliance costs, and may also file for Rent Guidelines Board increases.

If building is a co-op or condo, Owner must file a copy of the offering plan and a Co-op/Condo Exemption form to begin process of removal from Loft Board jurisdiction.

13. Loft Board issues final order setting initial regulated rents and removing building from the Loft Board's jurisdiction. The Loft Board directs the owner to register rental units with Department of Housing Preservation and Development (HPD) and Department of Housing and Community Renewal (DHCR).

14. Owner registers building with rental units with HPD and DHCR.


If you have any questions, please contact the Loft Board Public Information Officer at (212)-393-2603 or (212) 393-2616. You may also obtain additional information and a copy of the Loft Board Rules at www.nyc.gov/html/loft

Search Loft Board Orders
Loft Board Orders from 1996 to the present are now available online at the Center for New York City Law's Administrative Decision Web site.
Search Now
Resources