Registrants Project Checklists: Electrical Systems

Project Checklists contain project-specific details as they apply to the scope of work of the project to provide compliance with the NYC Construction Codes and other regulations. This section contains a list of tasks to assist with compliance.

Checklists include:

Pre-Permit Checklist

  • Construction Drawings. Make sure the Department-approved drawings clearly convey the project scope of work and that the drawings align correctly with the contracted work.

  • Scope Modification. Verify if changes need an amendment.

  • Insurance Requirements. Comply with the insurance requirements for General Liability insurance, Workers Compensation and Disability insurance. When required, update the General Liability insurance.

  • Special and Progress Inspections. Confirm the Owner has hired the Special and/or Progress Inspection Agency and that the required inspection information has been submitted, which is required to obtain a work permit.

Get a printable version.

On-going Project Work Checklist

  • Construction Drawings. Work defined in the Construction Documents must conform to the scope of work approved in the permit application documents. Minor variations, however, are allowed – see Minor Variations Memorandum. Please note certain changes may require an amendment.
  • Scope Modification. Verify if changes need an amendment
  • Site Safety. To minimize the risk of accidents and fire during construction, the LME/Contractor must maintain his/her work site in a safe condition.
  • Special and Progress Inspections. Coordinate the work schedule with the SIA to assure inspections are completed as required for each stage of the work.
  • Department Inspections. Request or self-certify the required inspections, by the completion of each stage of construction and obtain DOB sign-off for the completed work.
  • Self-Certification. If self-certifying the required inspections, be sure to submit a Notice of Intent to Self-certify. Self-certification inspection may be audited and inspected.

Get a printable version.

Project Completion Close-out Checklist

  • Department Inspections. Request or self-certify the inspections required for each stage of construction, and obtain a sign-off for the completed work.
  • Self-Certification. If self-certifying the required inspections, be sure to submit a Notice of Intent to Self-certify, which may be audited.
  • As-Built Submission. Coordinate installation with RDP for submission (RDP to submit PAA as required).
  • Final Sign-off. Make sure to complete all Department inspections and obtain a final sign-off of the completed work.

Get a printable version.