PA1 Construction Notices

PA1 Construction Notices

Project Area 1 (PA1) is concentrated in Manhattan's Lower East Side (LES) between Montgomery St. and East 15th St., including the East River Park. View upcoming East Side Coastal Resiliency (ESCR)-related travel advisories, construction bulletins and notices for the most up-to-date information on closures, detours, and restrictions for Project Area 1 (PA1). Please note, due to unforeseen conditions (weather, field conditions, etc.) it may become necessary to change some scheduled work locations and operations.

PA1 Weekly Construction Bulletin

PA1 Construction Bulletin - Week of May 23, 2022
Anticipated work schedule for 05/23/2022 to 06/05/2022

Active PA1 Community Advisories

Con Edison Utility Work in East River Park at Greenway Continues North | Spanish | Chinese
Ongoing until further notice
Under the ESCR project, Con Edison utility line upgrade work continues in ERP along the Greenway north to E. 10th Street. Park access points are located at E. Houston, E. 6th and E. 10th Streets pedestrian bridges. Access to Track & Field and restroom areas will be maintained. See the Site Access Plan for more details.  Please follow onsite signage.

Partial closure of Corlears Hook Park | Spanish | Chinese
Starting April 4, 2022, ongoing until further notice
Construction activities will necessitate the closure of portions of Corlears Hook Park, including the flagpole area.
To access open park areas use entrances at Jackson Street and west entrances on Cherry Street. For public access to ferry, use Corlears Hook Bridge. Please follow all on-site signage while closures are in effect to ensure safety. Noise and air monitors are in place.

Con Edison Utility Work at E. 10th Street between FDR Drive and Avenue D | Spanish | Chinese
Starting week of May 2, 2022
Con Edison will begin phased upgrades of their utility lines under the ESCR project contract. Parking restrictions will be in effect during this operation and will be communicated through on-site signage. One lane of traffic will be maintained at all times. See Advisory for map.

Sidewalk Closure at Delancey Street and FDR Drive | Spanish | Chinese
Ongoing until further notice
Construction activities will necessitate the closure of the sidewalk at Delancey Street between FDR Drive and Baruch Drive. This change will be in place 24 hours/day, 7 days/week. Traffic will be maintained and pedestrian detour is in effect. Please follow all signs and directions placed on-site to ensure safety. See Advisory for map.

Closure of Delancey Street Bridge & Park Areas South of Stanton Street | Spanish | Chinese
Starting on December 6, 2021
For public access to ferry use Corlears Hook Bridge. To access open park areas use entrances at E Houston Street, 6th Street Bridge, or 10th Street Bridge. See bicycle detour advisories. Closures include the amphitheater, southern athletic fields and basketball courts, lawn & water play area, Delancey Street Bridge, Brian Watkins Tennis Center, and dance circle. Please follow all signage while closures are in effect to ensure safety.

East River Greenway Closure Between Montgomery Street & E 10th Street | Spanish | Chinese
Starting on December 6, 2021
Construction operations in East River Park will require the following bicycle detour, 24 hours/7 days. To access ferry use Corlears Hook Bridge. To access open park areas use entrances at E Houston Street, 6th Street Bridge, or 10th Street Bridge.

Work begins in ESCR Project Area 1 | Spanish | Chinese
Starting the week of November 1, 2021
Phased work operations are scheduled to begin at East River Park. Closures within the Park and pedestrian detours will take place to accommodate equipment transport and construction fencing. Advisories and Bulletins will be posted here as developed. For vehicle and pedestrian safety, follow all signage while detours are in effect.


See archive Community Advisories and Weekly Construction Bulletins for PA1